Parking Alert - Fletcher Construction Project

   
ID: 63
Lots/Structures: N13
Starts: 06/28/2017
Ends: 10/31/2017

Details

A project to complete concrete, waterproofing and drain system repairs will begin at the Fletcher Parking Structure on Wednesday, June 28th. The first phase involves concrete repairs on the North end of the Plaza (patient parking area), moving to the South end on Monday, July 24th. 

Drain system repairs on the Plaza and level 5 will start on Monday, July 24th with the work taking place from 5 p.m. to 3:30 a.m.

Deck coating repairs on the Plaza level will take place in late August. 

Approximately 30 spaces will be closed at any one time. Anticipated project completion is October 31st.